Progress claims in construction are where a project’s cashflow is won or lost. Every month, the builder puts a value on the work done and the owner decides how much of it to pay. When both sides measure the same way, the process is routine. When they do not, a few percentage points of disagreement on each claim can turn into a cashflow crisis for the builder or an overpaid contract for the owner, and eventually a dispute. This guide explains how a progress claim should be prepared, how retention works, where front-loading and overclaiming creep in, and how an owner should assess a claim before paying it.

What a progress claim is

A progress claim is a builder’s or subcontractor’s request for payment for the work completed in a period, usually a month or a construction stage. It is measured against the contract sum, which is the agreed price for the whole job, broken down into a schedule of values: a list of trades or elements, each with its share of the contract price. Each claim shows how far along each item is, the value of that progress, what has already been paid and what is now due.

On residential work, claims are usually tied to stages such as slab, frame, lock-up, fixing and practical completion. On commercial projects they are more often monthly and measured line by line against the schedule of values, with approved variations added as separate items.

Progress claims also have legal weight. Security of payment legislation, such as the Building and Construction Industry Security of Payment Act 1999 in New South Wales and the Building and Construction Industry Security of Payment Act 2002 in Victoria, sets out how claims are made and how quickly they must be answered. A party that receives a payment claim and disagrees with it generally has to respond with a payment schedule within the time the Act allows, setting out what it will pay and why. Miss that step and the full amount claimed can become payable. These Acts generally do not apply to a homeowner building a house they will live in, but they apply across most commercial work and subcontracts.

How to prepare a progress claim

A good claim starts with a good schedule of values. Each line should be small enough to measure on site and priced at what that work genuinely costs, including its share of margin. A schedule with a handful of large lump sums invites argument, because nobody can agree what “50% of services” means. A schedule broken into trades, levels or areas can be checked against what is physically in place.

For each line, the claim records the percentage complete, the value of work to date, what was claimed previously and the amount claimed this period. The example below shows a simplified claim on a $600,000 commercial fitout.

ItemContract valueCompleteValue to date
Preliminaries$60,00040%$24,000
Demolition and strip-out$30,000100%$30,000
Partitions and ceilings$150,00050%$75,000
Electrical$120,00030%$36,000
Mechanical services$90,00020%$18,000
Joinery$80,0000%$0
Floor and wall finishes$70,0000%$0
Total$600,00030.5%$183,000

Illustrative figures only. They show how a claim is laid out, not what any item should cost.

If $110,000 was paid on earlier claims, the gross amount for this period is $73,000, before retention and GST. Approved variations are listed below the contract items with their own values, and unapproved variations are either left out or shown separately so they do not hold up payment of the rest.

The claim should be supported by evidence: site photos, delivery dockets for materials on site, subcontractor claims and, on larger jobs, a short report against the program. Materials delivered but not yet installed can sometimes be claimed, but only where the contract allows it and ownership has passed to the client.

How retention works

Retention is money the owner holds back from each claim as security against defects and incomplete work. A common arrangement in commercial contracts is to deduct 10% of each claim until the total held reaches 5% of the contract sum, then release half at practical completion and the rest at the end of the defects liability period. The exact rates and triggers are set by the contract, and some contracts allow a bank guarantee instead of cash retention.

In the example above, 10% retention on the $73,000 claimed this period would be $7,300, leaving $65,700 payable before GST, as long as the total held stays under the 5% cap of $30,000.

For builders, retention is a cashflow cost that needs to be planned from the start, especially when subcontractors are paid in full while the builder’s own retention is still held. For owners, it is the main leverage for getting defects fixed. Both sides should track retention on every claim so the running total and the release dates are never in doubt.

Front-loading and overclaiming

Front-loading

Front-loading happens when the early items in a schedule of values are priced above their true cost and the later items below it. Preliminaries, demolition and structure carry more than their share of the contract sum, so the builder is paid ahead of the real value of the work. It helps the builder’s cashflow in the early months. It also means the money left in the contract later on is less than the cost of the remaining work.

That is a problem for everyone. If the builder strikes trouble late in the job, there is not enough money left in the contract to cover the remaining work, and the owner is exposed. Lenders and experienced superintendents look for it from the first claim, and will often rebalance the schedule before any payment is approved.

Overclaiming

Overclaiming is claiming a higher percentage complete than is actually on site. Sometimes it is deliberate. More often it is optimism: a trade that is “nearly done” is claimed at 90% when the hardest 30% is still to come, or materials are claimed as installed before they are fixed. Small overclaims across many lines add up quickly, and once paid they are hard to recover.

The cost of overclaiming usually lands on the builder in the end. Claims get cut, trust drops, and every later claim is checked line by line. A claim that is measured honestly and backed by evidence gets paid faster.

How an owner should assess a progress claim

Assessing a claim is a site job, not a desk job. The assessor walks the site with the schedule of values, checks each line against what is physically in place, and adjusts the percentage complete where the claim runs ahead of the work. Photos, dockets and subcontractor claims support the assessment but do not replace the inspection.

Alongside the site check, the assessor should confirm that the schedule of values still adds up to the contract sum plus approved variations, that previous payments and retention are carried forward correctly, and that nothing has been claimed twice. Unapproved variations should be separated from the contract work so they can be dealt with on their own.

The last test is the cost to complete. Take the contract sum plus variations, subtract everything certified to date, and compare what is left with the realistic cost of the work still to be done. If the remaining money is less than that cost, the claims have been running ahead of the work, even if each one looked reasonable on its own.

Where security of payment laws apply, the assessment needs to be turned into a written payment schedule within the time allowed, giving the amount the owner will pay and the reasons for any reduction. A vague or late response can leave the owner liable for the full amount claimed.

The value of an independent claim assessment

Builders and owners both benefit from having claims measured by someone with no stake in the outcome. For a builder, an independently prepared claim is harder to dispute and quicker to pay, and a well-built schedule of values at the start avoids months of argument later. For an owner or lender, an independent assessment confirms that each payment matches the work on site and that enough money remains to finish the job.

Accent Estimating prepares and assesses progress claims for builders, owners and lenders, with site inspections, photographs and a cashflow statement showing what has been spent and what remains. For projects in Victoria, the team’s construction estimating services in Melbourne cover progress claims alongside residential, commercial and fitout costing.